What are the main stages of crane erection and dismantling?

Erection begins with preparing the foundation or rail track. Then, using a mobile crane, the tower is assembled, the slewing platform is installed, and the jib and counter-jib with counterweights are mounted. It concludes with the installation of the cabin, ropes, and electrical equipment.

Dismantling is done in the reverse order.

After erection, mandatory load tests and safety system checks are performed.