How long do delivery and erection of a tower crane take?
Transporting the crane to the site can take anywhere from one day (within a city) to a week (if the crane is being imported).
The erection process itself usually takes 2 to 4 working days, given favorable weather and site readiness.
Complex and very tall cranes may take longer to erect. The timeline is also affected by the need for an auxiliary mobile crane.